New Industrial Unit, Wiltshire

A trial pit and dynamic probe site investigation with in-situ soakaway testing (carried out in accordance with BRE 365) was carried out.

Pad foundations and a ground bearing slab were recommended. In-situ testing was carried out at a later date to confirm the suitability of the underlying re-compacted fill beneath the slab.

Waste Acceptance Criteria (WAC) testing classified the soil as Non-Hazardous, for off-site disposal purposes.